Enhancing Electric Grid Resilience Act · 119th Congress · Introduced Jul 22, 2026 · Latest action Jul 22, 2026

Official title

Enhancing Electric Grid Resilience Act

Official page
What it actually does · title is vague

This bill changes the Federal Power Act so that when a company builds a very large interstate power line (at least 1,000 megawatts) or upgrades a line by at least 500 megawatts, the company must tell the Federal Energy Regulatory Commission (FERC) how it will spread the building costs to the people who use electricity. FERC will make sure the costs are shared with customers in the area who will get the most benefit, like better reliability, lower prices, cleaner energy, and a stronger grid. The rule only applies to new or upgraded lines that are built after the law takes effect, and it does not change how other, smaller projects are paid for.

  • Rule: Any company that wants to own or run a new or upgraded interstate or offshore transmission line of national significance must file a tariff with FERC showing how the costs will be allocated.
  • Duty: FERC must require the tariff to allocate costs to customers in the planning region, roughly matching the anticipated benefits (reliability, economic, environmental, etc.).
  • Definition: "Transmission facility of national significance" includes new lines ≥1,000 MW or upgrades ≥500 MW that are completed after the law’s enactment, whether on land or offshore.
  • Cost Allocation Principle: Costs are to be shared based on a broad range of expected benefits, not just distance or usage, ensuring those who gain most pay more.
  • Who Gains/Loses: Customers in regions that receive the new or upgraded line may see higher electric bills to cover construction, while the overall grid becomes more reliable and resilient; other regions are not charged.
  • Exception: The bill does not affect FERC’s authority to approve cost allocation for transmission projects that are not classified as "national significance."
  • Potential Impact: By encouraging cost recovery for large projects, the bill could speed up building high‑capacity lines, including offshore lines that support renewable energy, but it may also shift financial burdens to ratepayers.

Title check: The title talks about "Enhancing Electric Grid Resilience," and the bill does mention resilience as one of the benefits used for cost allocation, but the main purpose of the law is to set rules for how the costs of large new or upgraded transmission lines are shared with customers. It does not directly create new resilience measures, so the title only loosely reflects the content.

AI-generated read, not yet human-reviewed · How these reads are made

Name in the news

No sourced news or social name stored. This page will not invent one.

How members voted

No roll call is stored on this bill yet.

PersonPartyVote