U.S. S 3287
Fair Allocation of Interstate Rates Act · 119th Congress · Introduced Dec 1, 2025 · Latest action Dec 1, 2025
This bill says that electric companies can’t charge people in one state for the cost of a power line that was built mostly to follow another state’s policy, unless the state where the person lives gives permission. The rule is meant to make sure each state pays for the power lines that benefit its own residents.
- Rule: Transmission providers may not allocate costs of a "covered transmission facility" to consumers in states that didn’t approve the project.
- Duty: The Federal Energy Regulatory Commission must write rules to enforce the new prohibition within 180 days.
- Exception: A state (or its designated public official) can give explicit consent, allowing its residents to be charged for the facility.
- Presumption: Only the state that created the policy behind the transmission line is considered a "cost causer"; other states’ residents are not.
- Who gains: Residents of states that did not approve the transmission project (they won’t be charged).
- Who loses: Transmission companies lose the ability to spread costs to out‑of‑state customers unless they get consent, and states that consent may still have to pay.
Title check: The official title, "Fair Allocation of Interstate Rates Act," accurately reflects the bill’s purpose of ensuring that interstate electric transmission costs are fairly assigned only to the states that benefit from or consent to the project.
AI-generated read, not yet human-reviewed · How these reads are made
No sourced news or social name stored. This page will not invent one.