U.S. HR 6983
PRICE Act · 119th Congress · Introduced Jan 8, 2026 · Latest action Jan 8, 2026
This bill says any big data center in the U.S. has to make all the electricity it uses itself. Starting in 2035, at least three‑quarters of that power must come from clean sources like solar or wind, and by 2040 it has to be 100% clean. If a data center doesn’t follow the rule, it could be fined up to $100,000 each day until it fixes the problem. The Energy Secretary must set up the fine system within 30 days of the law taking effect.
- Rule: Every data center (using 50 MW+ daily) must generate all of its own electricity.
- Clean‑energy requirement: ≥75% of that power must be from clean sources starting Jan 1 2035, and 100% by Jan 1 2040.
- Penalty: Violations can lead to civil penalties up to $100,000 per day until corrected.
- Administrative duty: The Secretary of Energy must create a penalty‑enforcement process within 30 days of enactment.
- Who gains: Clean‑energy companies may see more business; data centers face new costs and infrastructure work.
- Who loses: Data center operators may have higher capital and operating expenses, possibly passing costs to customers.
- Definition: “Clean energy source” includes solar, wind, battery, green hydrogen, hydropower, and geothermal.
Title check: The official title claims the bill prevents rate inflation for consumers, but the actual text only mandates data centers to produce their own electricity using clean energy, with no explicit connection to consumer energy rates.
AI-generated read, not yet human-reviewed · How these reads are made
No sourced news or social name stored. This page will not invent one.
How members voted
No roll call is stored on this bill yet.
| Person | Party | Vote |
|---|---|---|
| No individual votes stored on this bill. | ||