Ratepayer Bill of Rights Act of 2026 · 119th Congress · Introduced Aug 24, 2026 · Latest action Aug 24, 2026

Official title

Ratepayer Bill of Rights Act of 2026

Official page
What it actually does · title matches the text

This bill says that big data centers (places that store lots of computer information) must tell the public how much electricity and water they use, how much it will cost, and what kind of help they get from the government. The bill makes sure that families, farms, schools, hospitals, and small businesses don’t have to pay for the data center’s costs. Before a data center can start using water or electricity, an independent group has to check that it won’t hurt the community’s water supply or power reliability. The data center has to pay for all its own infrastructure, and any money it tries to shift onto utility bills must be paid back with interest. People living near a data center get advance notice, a chance to hear the details, and a public meeting to voice concerns.

  • Rule: Data centers using 50 MW of electricity or 100,000 gallons of water per day must publicly disclose their electricity and water use, infrastructure costs, rate impacts, and any government assistance.
  • Duty: Companies must pay all project‑driven costs themselves, post financial security, and can’t shift those costs to ratepayers through utility rates, riders, or surcharges.
  • Exception/Protection: Ratepayers (households, farms, schools, hospitals, small businesses) have the right not to be subsidized; any improper charges must be refunded with interest within 90 days.
  • Who Gains: Ratepayers, rural water users, farmers, ranchers, schools, hospitals, and local communities gain transparency and protection from hidden costs.
  • Who Loses: Large data center operators lose the ability to hide costs or receive undisclosed public subsidies and may face higher upfront financial responsibilities.
  • Additional Safeguard: Before water or electricity service is approved, an independent assessment must confirm sufficient supply for the community and that reliability won’t be harmed.
  • Public Participation: Residents must receive at least 60 days’ notice and have a local public meeting with cost and reliability studies available at least 30 days before a final decision.

Title check: The official title, "Ratepayer Bill of Rights Act of 2026," accurately reflects the bill’s focus on protecting utility customers (ratepayers) by requiring disclosures and preventing data centers from passing their costs onto the public.

AI-generated read, not yet human-reviewed · How these reads are made

Name in the news

No sourced news or social name stored. This page will not invent one.

How members voted

No roll call is stored on this bill yet.

PersonPartyVote
No individual votes stored on this bill.