BADGES for Native Communities Act · 118th Congress · Introduced Feb 16, 2023 · Latest action Dec 17, 2024
This bill tells the Federal Energy Regulatory Commission (FERC) to change the way it handles requests to connect new power plants to the electric grid. Within 90 days, FERC must start a rulemaking to make the "interconnection queue"—the list of projects waiting to connect—more flexible. The new rules would let transmission companies move projects that provide reliable, dispatchable power higher up in the queue if they show that doing so will make the grid safer and more resilient. The companies must also let the public comment and give regular reports about grid reliability.
- Rule: FERC must begin a rulemaking within 90 days to address interconnection queue inefficiencies.
- Duty: Transmission providers must submit proposals to prioritize dispatchable power projects, showing need and benefits to grid reliability and resilience.
- Public Process: Proposals require a public comment period and stakeholder engagement before submission to FERC.
- Reporting: Transmission providers must regularly report to FERC on grid reliability, resilience, and actions taken under the Act.
- Scope: Only new dispatchable power projects that improve grid reliability and resource adequacy are eligible for higher queue priority.
- Impact on Others: Projects that are not deemed dispatchable or do not improve reliability may stay lower in the queue, potentially delaying them.
Title check: The official title refers to "BADGES for Native Communities Act," which has no relation to the bill's content about reforming the electric grid interconnection queue and improving grid reliability.
AI-generated read, not yet human-reviewed · How these reads are made
No sourced news or social name stored. This page will not invent one.
How members voted
No roll call is stored on this bill yet.
| Person | Party | Vote |
|---|---|---|
| No individual votes stored on this bill. | ||