South Dakota · introduced
South Dakota SB 232
impose a one-year moratorium on the construction or expansion of hyperscale data centers. · 2026 session · Introduced Feb 4, 2026 · Latest action Feb 18, 2026
Official title
impose a one-year moratorium on the construction or expansion of hyperscale data centers.
Official pageWhat it actually does · title matches the text
The bill would stop any new building or expansion of very large data centers for one year.
- Rule: A one‑year moratorium on construction or expansion of hyperscale data centers.
- Duty: All parties must halt any projects or upgrades to such data centers during the moratorium.
- Exception: No exceptions are mentioned in the bill.
- Who gains: Groups that oppose large data center projects (e.g., environmental or community groups) could benefit from the pause.
- Who loses: Companies that build or expand hyperscale data centers, their investors, and potentially workers tied to those projects.
Title check: The official title describes exactly the single action the bill proposes—a one‑year moratorium on constructing or expanding hyperscale data centers.
AI-generated read, not yet human-reviewed · How these reads are made
Name in the news
No sourced news or social name stored. This page will not invent one.
How members voted
Yea 5 · Nay 3 · 2026-02-18 · Official source
| Person | Party | Vote |
|---|---|---|
| Carl Perry senate · 3 | R | yea |
| Chris Karr senate · 11 | R | nay |
| Curt Voight senate · 33 | R | not_voting |
| Jim Mehlhaff senate · 24 | R | yea |
| Kevin Jensen senate · 16 | R | nay |
| Liz Larson senate · 10 | D | yea |
| Randy Deibert senate · 31 | R | yea |
| Steve Kolbeck senate · 2 | R | yea |
| Tom Pischke senate · 25 | R | nay |